Cooling Tower Fill Replacement
Location: Kooragang Island, NSW
Job Type: Cooling Tower Fill Replacement
Client: Orica
Contractor: Marley Flow Control

The Problem
Orica’s cooling tower at the Kooragang Island facility required a full fill replacement to maintain thermal efficiency and structural integrity. The challenge was to complete the work within a tight shutdown window, coordinating with multiple contractors and ensuring zero disruption to plant operations.
Our Approach
Marley Flow Control executed a precision-based strategy to meet the shutdown deadline:
-
Fill Removal & Replacement:
-
Removed aging fill material from the tower’s wetted zone
-
Installed new Marley polypropylene splash fill bars and FRP grids for improved thermal performance
-
-
Structural Timber Repairs:
-
Replaced compromised timber within the wetted zone to restore integrity and support
-
-
Mechanical Overhaul:
-
Removed and reinstalled mechanical components including motor, driveshaft, gearbox, and fan
-
Conducted laser alignment to ensure optimal performance
-
-
Hardware Upgrades:
-
Replaced all bolts and anchor brackets in the wetted zone
-
-
Execution Methodology:
-
Fill removed bottom-up for safe access
-
New fill installed top-down to ensure alignment and airflow consistency
-
All works completed in accordance with contract specifications and safety protocols
-
The Result
This project demonstrated Marley Flow Control’s ability to deliver high-performance cooling tower upgrades under time-sensitive conditions, with precision and safety at the forefront.
​
-
Completed Within Shutdown Window
-
Zero Safety Incidents
-
Improved Cooling Efficiency
-
Restored Structural Integrity