Industrial Cooling Tower Repair

CS Energy - Biloela, Queensland

Biloela-QLD_2-e1595472808769-600x800.jpg

The Problem

Marley Flow control was engaged by CS Energy to complete replacement of the unit C cooling tower fan deck. Due to the time frame of the shutdown, it was imperative that the fan deck replacement was completed in the most time efficient manner. As the largest cooling towers in the southern hemisphere, the experience of the Marley flow crew ensured that that fan deck was completed on time and to the satisfaction of the client.

Biloela-QLD_4-600x800.png

Our Approach

Marley Flow created a detailed methodology that involved prefabricating the fan deck components and packed them in the specific laying order. This eliminated the high risk of cutting the fan deck in the plenum, and leads to greater quality control of the deck boards. Additionally,

Biloela-QLD.png

The Solution

Marley developed bespoke tools that allowed simple and effective lifting of the fan cowling, preventing the need for a 120T crane throughout the duration of the job, and simplifying the onsite tasks. This pre-project organisation allowed Marley Flow to complete the job within the 3-week time frame, and without any injuries.

Create Your First Project

Start adding your projects to your portfolio. Click on "Manage Projects" to get started

Project Title

Project Type

Photography

Date

April 2023

This is where the project description goes. Give an overview or go in depth - what it's all about, what inspired you, how you created it, or anything else you'd like visitors to know. To add Project descriptions, go to Manage Projects.

bottom of page